Construction process

Modular building construction looks like Lego blocks that result in ecological sensitivity, safety, and above-average functional living units. This is how the Podljubnik Kindergarten in Škofja Loka was created, which was constructed in just a month.

24 September 2009 – undertaking of works at the construction site and erection of first modular units




30 September 2009 – placement of central heating pipes and electricity cables




08 October 2009 – wooden roof framework assembly




11 October 2009 – laying of PVC lining, finishing of the roof, wooden projecting roof erection




22 October 2009 – sanitary ceramics assembly and conclusion of other contractual works




29 October 2009 – conclusion of all contractual works